Manufactured in Hamilton, Ontario since 1933
Engineering SurveysMaryland Brush

Continuous Galvanizing Line: Filtration and ROI

The line drained its tanks every six weeks to control contamination. The real problem was the filtration system. A continuous galvanizing line was draining and cleaning its tank systems every six weeks. Management wanted to know what it would cost to fix the root cause instead of paying for the symptoms on a repeating schedule.

13
Findings, prioritized by operational impact, with an ROI model attached
6 wk
Pump-out cycle that had become the line's main method of contamination control
Close-up of galvanized steel bars showing the coated surface

The cost of treating symptoms every six weeks

A continuous galvanizing line was draining and cleaning its tank systems every six weeks to remove accumulated contamination. Each pump-out consumed chemicals, energy, pumping services, and wastewater treatment. Management wanted to understand the cost of solving the root cause rather than paying for the symptoms again every cycle.

Discovery

Felton MBC met with the engineering and reliability teams to review the line’s cleaning process, which ran through alkali cleaning, brush scrubbing, electrolytic cleaning, and a final rinse. A full engineering survey was scheduled.

Engineering Survey

Felton MBC engineers spent four days on site working alongside the mill’s mechanical, process, instrumentation, and reliability personnel. The survey produced thirteen findings, and filtration was the primary issue. The four largest findings are below.

01. Filtration capacity was inadequate

The system removed only a small percentage of the soil load from circulation, so contaminants kept cycling through the cleaning system, the furnace, and the zinc pot. The six-week pump-out schedule had become the line’s main method of contamination control.

02. The alkali dunk tank re-contaminated the strip

Turbulence in the tank kept accumulated solids suspended, and the sink roll pressed those contaminants back into the strip surface instead of removing them.

03. Backup rolls were out of position

The roll placement prevented proper strip shape control entering the brush contact area.

04. Several spray headers provided little or no cleaning benefit

Some headers were not aimed at the brush-strip contact zone and added little to the process.

Recommendations

Felton MBC delivered a thirteen-point improvement roadmap prioritized by operational impact. The primary recommendation was a high-efficiency filtration system that continuously removes most suspended solids and iron fines.

The roadmap also covered converting the alkali dunk tank to a vertical pre-cleaning system, removing spray headers that added no value, repositioning the backup rolls, upgrading brush construction, and moving to a progressive filament grit strategy.

ROI analysis

The report projected annual savings from reduced caustic consumption, lower water usage, lower wastewater treatment costs, and the elimination of routine pump-outs, with each category quantified against the mill’s current operating costs.

Implementation path

A sequenced plan combining capital improvements, meaning the filtration system and vertical pre-cleaning, with near-term operational changes the mill could start immediately.

Implementation

The project is in progress. Felton MBC is working with the customer’s engineering team to sequence the capital improvements and the near-term operational changes. Results will be validated through a follow-up engineering audit once implementation is complete.

What four days on site produced

  • A thirteen-point improvement roadmap prioritized by impact
  • An ROI model with projected annual savings
  • Quantified savings across chemicals, water, and waste treatment
  • A sequenced plan covering both capital and operational changes

Key takeaway

Filtration upgrades rarely attract capital attention because they do not directly increase production output. Their impact shows up elsewhere on the P&L, in lower chemical consumption, lower wastewater costs, reduced maintenance, and better downstream reliability. Those savings often justify the investment on their own, before any production benefit is counted.

The Engineering Survey was built to make that case. A thirteen-point roadmap with an ROI model attached gives the engineering team something to bring to capital planning that pays for itself in operating costs.

Official Disclaimer

The information contained in this document is based on tests which are believed to be reliable. Since actual conditions of use may vary and are beyond the control of FELTON the product's specified characteristics cannot be guaranteed and are offered solely for the buyer's evaluation and verification. There are no warranties, representations or conditions, expressed or implied, of any kind, including, but not limited to, merchantability or fitness for a particular purpose made by FELTON of its officers, employees or affiliates, in connection with the sale of the products described in the document. Accordingly, the purchaser and each user assumes all risks and liability in connection with their use of such products. Nothing contained herein is to be construed as permission, recommendation or inducement by FELTON to use any product or process so as to infringe or conflict with any patent. Further, it is the user's obligation to utilize this material in full compliance with health, safety and environmental regulations.

Most of these problems start in the cleaning section

Short brush life, coating defects, climbing caustic costs, and unplanned downtime usually trace back to the cleaning section. An Engineering Survey finds the cause.